PRINCE2 Project Management

page · Updated 2026-10-05T01:49:57 · Original source

Purpose

This is the project-control layer for the Great House Farm / Tŷ Mawr evidence, history, replica-museum and remedy programme. It uses PRINCE2 Project Management Version 7, tailored: a defined mandate, controlled scope, stage-based planning, work packages, measurable task groups, monthly highlight reports, and escalation of issues and risks.

Current control date: 1 October 2026. The management record is retrospective as well as forward-looking. Historical monthly reports are backdated to the project evidence-access chronology and are not presented as contemporaneous records if they were reconstructed later.

Control pageFunction
Project MandateWhy the project exists, authority, intended benefits, boundaries and success criteria.
Project BriefWhat will be delivered, for whom, scope, assumptions, constraints, outputs and acceptance criteria.
Project PlanMilestones, work packages, task groups, measures, dependencies and stage sequencing.
Delivery BreakdownDetailed work-breakdown structure: milestone → work package → task group → measurable task.
Monthly Highlight ReportsOne report per month with Plan, Performance, Issues/Risks/Concerns and Plan Moving Forward.
Project AnalyticsManagement statistics, trend measures, throughput, backlog, external-response performance and delivery health.

Management principles

  • Evidence before conclusion. A missing record is a recovery task, not proof of what the record contained.
  • Separate fact, family evidence and inference. Management reporting must preserve that distinction.
  • Every material action gets a control home. Requests, reviews, disclosures, research questions, corrections and museum outputs must belong to a work package and task group.
  • External dependency is measurable. Waiting for a public body is not counted as an internal delivery failure, but the elapsed time and next escalation are tracked.
  • Monthly control is cumulative. Each month’s plan is derived from the previous month’s forward plan and the current evidence of performance, issues and risk.

Status vocabulary

StatusUse
Not startedApproved task group has no recorded activity.
ActiveWork is underway and has a current next action.
Awaiting external responseThe next controllable action is with an external body.
BlockedA dependency prevents meaningful progress; an escalation route is recorded.
CompleteAcceptance criterion met and supporting evidence linked.
Closed / archivedNo further action planned, with the rationale recorded.
Re-openedPreviously completed work has returned to active investigation because new evidence changed the control position.

See Mandate · Brief · Plan · Delivery Breakdown · Highlight Reports · Analytics.

Justice Programme

The Justice Programme is the legal/public-accountability sub-programme. It converts the evidence base into a controlled strategy for title determination, reopening/set-aside analysis, public inquiry, institutional remedy, property restoration, potential compensation, narrative justice and the Argentina replica museum.

Justice Programme · Justice Mandate · Justice Brief · Justice Plan

PRINCE2 7 master controls

Use the PRINCE2 7 Compliance & Control Manual for the method, the PRINCE2 Control Registers for risk/issue/change/quality/lessons/decisions, the G0 PID Pack for the four project PIDs, and the October S0 Stage Plan & Control Register for execution.

Agent editing controls

All agents working on the Wiki must follow the Site Agent Operating Rules — Evidence, Links, Citations & Change Control. No substantive factual statement should be added without a supporting source/hyperlink where available. Repeated statements must link to the canonical source. Material changes must pass the relevant PRINCE2 quality, issue/change, risk and decision controls.

Name/location reference: Great House Farm — Name & Location Variations (historical spellings and Llandough-juxta-Penarth location forms).

Browse mirror index